Electrical upgrade design works were required for this early 1800s themed tourism attraction in Ironbridge.
The management team were looking to introduce an educational learning centre 100 meters from the existing LV equipment.
They needed to ensure that their existing network was capable of taking this additional load.
We therefore carried out existing testing of circuits, checked discrimination of devices and ensured the earthing standards were up to the 18th Edition wiring regulations.
The site now has a new incoming LV panel board complete with micrologic MCCB’s and a dedicated sub-main awaiting connection into their learning hub.
We are confident we have updated their LV equipment to the best of our ability offering the site a safe, practical and long lasting design / installation.